You are here: start » na » reporting » wp_10_period_2
ACHIEVEMENTS IN REPORTING PERIOD:
⇐ 28sep | 2009 as whole | |
# eligible hours | 403.5 | 580.5 |
# observations | 47 | 62 |
from # proposals | 26 | 37 |
The numbers for 2009 as a whole include observations on the block schedule
for the upcoming Oct/Nov session, plus known e-VLBI observations coming
up 29-30 Sep. There are a further 4 e-VLBI days >= Oct, but there are
no specific schedules for those yet. Of course, some of the scheduled
Oct/Nov observations may not take place (weather, etc.), and there may
also be some not-yet-proposed target of opportunity observation.
For the following 12 months, one would expect similar numbers of
eligible hours. The ~580 expected for 2009 is actually a record
going back to the beginning of FP6 EVN TNA (those 5 years had
numbers of eligble hours of [338, 253.5, 368, 492, 489.5] from 2004-8).
The contracted value per year in FP7 is 115, so there's no problem
meeting that (happened already in the Feb/Mar session).
There have been 5 data-reduction visits so far (total of 34 days), made
under 4 proposals. The project summary for each of these is on file here.
There has been an additional data-reduction visit, but we're still
waiting on the project summary, so no reimbursement has been made
for that one yet. In terms of the questionnaires, I haven't started
nagging a lot yet. The web forms weren't available yet when I was
sending around the post-block-schedule e-mails to PIs for the Feb/Mar &
May/Jun sessions. A revised TNA blurb about the new forms has been
sent out to the Oct/Nov session PIs (but of course those observations
most likely won't be completely analyzed by the PIs before the end
of the year) – I need to send that to the previous session PIs also,
now that the new forms are available. Some of the earlier project summaries
that we do have in were also completed before the new FP7 form was ready,
so they use the FP6 one.B
PROBLEMS/ISSUES: Making a machine-completable project summary form
was a step forward from the situation in FP6, where a number of PIs
complained about having to print out a blank form and fill it in by
hand. I take it for granted now that some PIs, as in FP6, will comlain
about the multiplicity of reporting required: a project summary to
“enable” travel reimbursements plus an EC questionnaire plus a virtually
equivalent RadioNet questionnaire.
At the most immediate level, only
PIs wanting to get reimbursement for data-reduction trips explicitly
benefit from completing those feedback forms, and then it's only the
project summary that's significant – whereas it's the receipt (or not)
of the EC questionnaire that keeps Brussels happy/angry at the program
as a whole.
I'd think the number of questionnaires getting returned
to Brussels would increase if the motivations of the program and the PIs
could be aligned better – is we could somehow intercept the Brussels
questionnaire to use it's completion as the authorization for reimbursement.
This apparently wasn't possible in FP6 via Jodrell.
FORWARD LOOK: The EVN TNA should easily make its contracted hours
each year, thus the payments going to the stations should be constant
over individual years (unless the board decides to adjust hours claimed
per year, as happened in FP6). So far, there's no sign of too rapid
spending in the travel – but this comprises just 2 PC meetings, 1 CBD
meeting, and the data-reduction visits mentioned above (all from just
the Feb/Mar session so far – the data reduction visits natrually lag
the observations by 3-6 months or so.