Achievements in reporting period:
Good progress has been made which includes very encouraging noise, bandwidth and rejection figures on several mixer and cryogenic amplifier prototypes.
Problems / Issues
All tasks made good progress since the beginning of the year, except for the photonic local oscillator (AMSTAR+ Task 2). Problems are: 1) difficulty in phase-locking the lasers, despite the use of new laser sources; 2) a shortage of manpower at RAL (the group in charge of this sub-task) linked to the heavy involvment of the group in the integration of ALMA front-end receivers (RAL hosts the ALMA European Integration Center). We will see how this problem may be solved. It remains that the photonic LO sub-task is not essential for Task 2, as we have an alternate solution available which consists in using conventional Gunn LOs.
So, there is no red flag.
Forward Look With the 6-month prolongation of the JRA, theer should be no problem in reaching the main goals of all 4 tasks.
Deliverables are reports and a test on telescope.
Financial Report *
By Excel Sheet